PREPARATION FOR CASTING THE RSPTN BASEMENT FLOOR ELEVATION
CP PUMP SETTING PROCESS FOR BASEMENT FLOOR AREA RSPTN
RSPTN BASEMENT FLOOR CASTING WORK ( 70 M3 ) K225
PLASTERING WORK IN THE AREA OF RSPTN LT.01 GRID 1A-1H
PLASTERING WORK IN THE AREA OF RSPTN LT.01 GRID 1A-1H
CONTINUE CASTING THE FLOOR ELEVATION. BASEMENT RSPTN
CONTINUE CASTING THE FLOOR ELEVATION. BASEMENT RSPTN
PROGRESS OF SLAB AND BEAM REINFORCEMENT WORK ON 4TH FLOOR RSPTN ZONE 4 A
PROGRESS OF RSPTN TOP FLOOR SCAFFOLDING
CASTING WORK SW 1 AND COLUMN AXLE D4 RSPTN ( 13 M3 ) K400
CASTING WORK SW 1 AND COLUMN AXLE D4 RSPTN ( 13 M3 ) K400
SETTING UP THE RSPTN STAIR FORMWORK (FLOOR 3-5) CHECK DIMENSIONS AND REPAIRING
SETTING FORMWORK FOR SW 5 RSPTN STAIRS (FLOORS 3 – 4) CHECK DIMENSIONS AND REPAIRING
PROGRESS OF SLAB AND BEAM REINFORCEMENT WORK ON 4TH FLOOR RSPTN ( ZONE 4 A)
SETTING UP THE FORMWORK FOR THE RSPTN RAMP COLUMNS, FLOORS 2-3 (CHECK THE REINFORCEMENT AND DIMENSIONS
PREPARATION FOR CASTING SLABS AND BEAMS FLOOR 4 RSPTN ZONE 4 A (K400) CHECK CLEANLINESS, DIMENSIONS, AND REPAIR
SW 2 RSPTN REINFORCEMENT WORK (CHECK DIMENSIONS AND REINFORCEMENT
CHECK THE DIMENSIONS AND FIXINGS OF RSPTN ZONE 4B STAIRS (FLOOR 1-2)
SLAB AND BEAM CASTING WORK ON FLOOR 4 RSPTN ZONE 4A (K400)
COMPRESSION TEST K400 CONCRETE (9 DAYS AND 28 DAYS) 2 SAMPLES + 6 SAMPLES
BASEMENT FLOOR CASTING WORK RSPTN 80 M3 ( K225 )
CHECK THE VERTICALITY OF THE 04TH FLOOR COLUMN
SHEAR WALL CASTING (SW5) RSPTN FLOOR ROOF
WORK TO REPAIR RSPTN RAMPS LT 2-3
CURING FLOOR 4 RSPTN (ZONE 4 A)
ROOF TOP FLOOR SLAB AND BEAM REINFORCEMENT WORK ELV+24,900 ( ZONE 2 )
COLUMN CASTING WORK ON 4TH FLOOR RSPTN ZONE 4A ( 4 UNITS ) K400
PROGRESS OF REFILLING RSPTN RAM 2-3
ROOF FLOOR PLATE CASTING, RSPTN ELV BUILDING. +24.9
INSTALLATION OF WF STEEL ANCHORS ON COLUMN TOPS ON FLOOR 4 RSPTN ZONE 4 A
FORMWORK SETTING SW 1 TOP RSPTN
PROGRESS OF IRC MAIN STAIRS, FLOORS 1-2 (CHECK DIMENSIONS AND REINFORCEMENTS
CASTING OF FLOOR RAMPS 2 – 3 RSPTN
CHECK THE VERTICALITY OF THE SW 2 FLOOR 3 RSPTN FORMWORK
SW 2 FLOOR 3 RSPTN CASTING WORK
PLASTERING WORK IN THE AREA OF RSPTN LT.01 GRID 1A-1H